EstatePass
Business & FinanceOperationseasy10% of exam part

In Critical Path Method (CPM) scheduling, what is the float time for activities that are on the critical path?

Correct Answer

D) Zero days

Activities on the critical path have zero float time by definition, meaning any delay in these activities will delay the entire project. Float time only exists for non-critical path activities.

Answer Options
A
Determined by the project manager
B
Equal to the project duration
C
One day minimum
D
Zero days

Why This Is the Correct Answer

Activities on the critical path have zero float time by definition because they represent the longest sequence of dependent activities through the project network. Any delay in a critical path activity directly extends the project completion date since there is no buffer time available. Float time (also called slack) only exists when an activity can be delayed without affecting the project end date, which is impossible for critical path activities.

Why the Other Options Are Wrong

Option B: Equal to the project duration

Float time is not determined by the project manager's discretion but is mathematically calculated based on the network diagram and activity durations. Critical path activities will always have zero float regardless of what the project manager wants or decides.

Option C: One day minimum

One day minimum is incorrect because critical path activities have exactly zero float, not a minimum of one day. Having any float time, even one day, would mean the activity is not on the critical path by definition.

Memory Technique

Think 'CRITICAL = ZERO WIGGLE ROOM' - critical path activities are so important that there's zero time to wiggle or delay them

Reference Hint

Look up 'Critical Path Method' or 'Project Scheduling' in construction management references, typically found in project management chapters

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.