EstatePass
Business & FinanceOperationseasy10% of exam part

In CPM scheduling, what happens to the project duration when an activity on the critical path is delayed?

Correct Answer

C) Project duration increases by the same amount as the delay

Activities on the critical path have zero float, so any delay in a critical path activity directly increases the project duration by the same amount. This is why critical path activities require careful monitoring.

Answer Options
A
Project duration may increase depending on other activities
B
Project duration remains unchanged
C
Project duration increases by the same amount as the delay
D
Project duration decreases due to schedule compression

Why This Is the Correct Answer

Activities on the critical path have zero float (slack time), meaning there is no buffer time available to absorb delays. When any activity on the critical path is delayed, that delay directly extends the overall project completion date. Since the critical path determines the minimum project duration, any delay to critical path activities automatically increases the total project duration by exactly the same amount as the delay.

Why the Other Options Are Wrong

Option B: Project duration remains unchanged

This is incorrect because critical path activities have no float to absorb delays. Any delay to a critical path activity must extend the project duration since these activities determine the longest path through the project network.

Option D: Project duration decreases due to schedule compression

This is incorrect because delays cannot cause schedule compression or duration decreases. A delay by definition extends time, and critical path delays specifically extend the overall project duration.

Memory Technique

Think 'Critical = No Cushion' - critical path activities have no time cushion (float), so any delay hits the project finish date directly, like a domino effect with no buffer to stop it.

Reference Hint

Look up CPM (Critical Path Method) scheduling in the project management or scheduling chapter of your contractor reference manual, specifically the section on float/slack calculations.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.