EstatePass
Business & FinanceOperationshard10% of exam part

In CPM scheduling, what does the term 'free float' represent?

Correct Answer

B) Time an activity can be delayed without affecting any successor activities

Free float is the amount of time an activity can be delayed without affecting the early start of any immediately following activities. This is different from total float, which considers impact on the entire project.

Answer Options
A
Time an activity can be delayed without affecting the project completion
B
Time an activity can be delayed without affecting any successor activities
C
The difference between optimistic and pessimistic time estimates
D
The shortest possible duration for completing an activity

Why This Is the Correct Answer

Free float specifically measures the amount of time an activity can be delayed without affecting the early start time of any immediately following successor activities. It is calculated as the difference between the early finish of the current activity and the earliest early start of all successor activities. This concept is crucial in CPM scheduling because it identifies activities that have scheduling flexibility without creating downstream delays. Free float is always less than or equal to total float and focuses on local impact rather than overall project impact.

Why the Other Options Are Wrong

Option C: The difference between optimistic and pessimistic time estimates

This describes total float, not free float. Total float considers the impact on the entire project completion date, while free float only considers the impact on immediate successor activities.

Option D: The shortest possible duration for completing an activity

This describes the range in PERT time estimates, not free float. Free float is a scheduling concept related to activity delays, not time estimation variability.

Memory Technique

Think 'FREE your successors' - free float is the time you can delay without making your successor activities start late. Total float affects the whole project, but FREE float only affects what comes immediately after.

Reference Hint

Look up CPM scheduling methods in the project management or scheduling chapter, specifically the section on float calculations and critical path analysis.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.