EstatePass
Business & FinanceOperationsmedium10% of exam part

In CPM scheduling, if an activity has an Early Start of day 10, duration of 5 days, and Late Finish of day 20, what is the activity's total float?

Correct Answer

B) 5 days

Total float = Late Finish - Early Start - Duration = 20 - 10 - 5 = 5 days. This represents how many days the activity can be delayed without affecting the project completion date.

Answer Options
A
10 days
B
5 days
C
0 days
D
15 days

Why This Is the Correct Answer

Option B is correct because total float is calculated using the formula: Late Finish - Early Start - Duration. With the given values (LF=20, ES=10, Duration=5), the calculation yields 20 - 10 - 5 = 5 days. This means the activity can be delayed up to 5 days without impacting the project's critical path or overall completion date. Total float represents the scheduling flexibility available for non-critical activities.

Why the Other Options Are Wrong

Option C: 0 days

Option D is incorrect because 15 days seems to be adding the duration to the Early Start (10 + 5) rather than properly applying the total float formula.

Option D: 15 days

Option C is incorrect because 10 days appears to be confusing the Early Start date with the actual float calculation, ignoring the duration component of the formula.

Memory Technique

Remember 'LED' for the total float formula: Late finish minus Early start minus Duration (LF - ES - D = Total Float)

Reference Hint

Look up CPM scheduling and float calculations in the project management or scheduling chapter of your contractor reference manual, typically found under 'Critical Path Method' or 'Network Analysis'.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.