EstatePass
Business & FinanceOperationsmedium10% of exam part

In a CPM schedule, if Activity X has an Early Start of day 10, duration of 4 days, and total float of 2 days, what is its Late Finish?

Correct Answer

A) Day 16

Early Finish = Early Start + Duration = 10 + 4 = 14. Late Finish = Early Finish + Total Float = 14 + 2 = 16.

Answer Options
A
Day 16
B
Day 14
C
Day 20
D
Day 18

Why This Is the Correct Answer

To find Late Finish in CPM scheduling, you must first calculate the Early Finish by adding duration to Early Start (10 + 4 = 14). Then, Late Finish is calculated by adding the total float to the Early Finish (14 + 2 = 16). This represents the latest day the activity can finish without delaying the project, accounting for the available float time.

Why the Other Options Are Wrong

Option B: Day 14

Day 14 is the Early Finish, not the Late Finish. This answer fails to account for the 2 days of total float that allows the activity to finish later without impacting the critical path.

Option D: Day 18

Day 20 appears to double-count the float or use an incorrect calculation method. This significantly overestimates when the activity can finish.

Memory Technique

Remember 'ELF': Early finish + Late float = Late Finish. The float gives you extra time beyond when you could finish early.

Reference Hint

Look up CPM (Critical Path Method) scheduling formulas in the Project Management or Construction Scheduling chapter of your reference manual

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.