In a cost-plus contract with a 12% fee, the contractor incurs $450,000 in allowable costs and $25,000 in non-allowable costs. What is the contractor's total compensation?

Correct Answer

D) $507,000

Total compensation = Allowable costs + Fee on allowable costs = $450,000 + ($450,000 × 12%) = $450,000 + $54,000 = $504,000. Non-allowable costs are not reimbursed and don't earn fee.

Answer Options
A
$504,000
B
$529,000
C
$475,000
D
$507,000

Why This Is the Correct Answer

Total compensation = Allowable costs + Fee on allowable costs = $450,000 + ($450,000 × 12%) = $450,000 + $54,000 = $504,000. Non-allowable costs are not reimbursed and don't earn fee.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.