EstatePass
Project MgmtConstructioneasy63% of exam part

How many cubic yards of concrete are needed for a foundation wall that is 100 feet long, 8 inches thick, and 6 feet high?

Correct Answer

B) 14.8 cubic yards

Volume = 100' × (8/12)' × 6' = 400 cubic feet. Converting to cubic yards: 400 ÷ 27 = 14.8 cubic yards.

Answer Options
A
22.2 cubic yards
B
14.8 cubic yards
C
17.8 cubic yards
D
400 cubic feet

Why This Is the Correct Answer

To find concrete volume, we must first calculate the volume in cubic feet using consistent units, then convert to cubic yards. The wall dimensions are 100 feet long × 8/12 feet thick (converting inches to feet) × 6 feet high = 400 cubic feet. Since there are 27 cubic feet in one cubic yard, we divide 400 by 27 to get 14.8 cubic yards.

Why the Other Options Are Wrong

Option A: 22.2 cubic yards

This answer of 17.8 cubic yards suggests an error in the calculation, possibly from incorrectly converting the 8-inch thickness or making an arithmetic mistake in the division by 27.

Option C: 17.8 cubic yards

This answer of 22.2 cubic yards is too high and likely results from a calculation error, possibly from not properly converting the 8 inches to feet or making an error in the final division.

Option D: 400 cubic feet

While 400 cubic feet is the correct intermediate calculation, the question asks for cubic yards, not cubic feet, making this answer incomplete and in the wrong units.

Memory Technique

Remember '27 to fly' - there are 27 cubic feet in a cubic yard (3×3×3), and concrete calculations need to 'fly' from cubic feet to cubic yards for ordering.

Reference Hint

Look up concrete volume calculations and unit conversions in the construction materials or estimating chapter of your reference manual.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.