A Orlando material supplier first furnished materials 45 days ago on a private job and has not served a notice to owner. What should the supplier's compliance file show?

Correct Answer

B) serve now

Florida's construction lien notice-to-owner rule uses a 45-day outside period from first furnishing, subject to statutory conditions.

Answer Options
A
record claim of lien
B
serve now
C
request final affidavit
D
release retainage

Why This Is the Correct Answer

Florida's construction lien notice-to-owner rule uses a 45-day outside period from first furnishing, subject to statutory conditions.

Why the Other Options Are Wrong

Option A: record claim of lien

record claim of lien skips the written authority, scope, price, notice, or release control needed for notice to owner timing.

Option C: request final affidavit

request final affidavit skips the written authority, scope, price, notice, or release control needed for notice to owner timing.

Option D: release retainage

release retainage skips the written authority, scope, price, notice, or release control needed for notice to owner timing.

Memory Technique

Florida'S before dollars; construction before balance in Supplier'S Office.

Reference Hint

Open-book path: tab Florida Statutes Chapter 713 to Section 713.06, Notice to Owner timing; confirm the Florida statutory or Department of Revenue rule before answering.

Was this explanation helpful?

More Business & Finance Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.