A Mount Dora aging report lists $28,600 at 31-60 days, $17,400 at 61-90 days, and $9,200 over 90 days. What amount is over 60 days past due?

Correct Answer

C) $26,600

Use only the aging buckets requested in the question.

Answer Options
A
$46,000
B
$37,800
C
$26,600
D
$55,200

Why This Is the Correct Answer

Use only the aging buckets requested in the question.

Why the Other Options Are Wrong

Option A: $46,000

$46,000 is above the supported result for receivables aging; it likely adds an unsupported amount or compares the wrong financial base.

Option B: $37,800

$37,800 is above the supported result for receivables aging; it likely adds an unsupported amount or compares the wrong financial base.

Option D: $55,200

$55,200 is above the supported result for receivables aging; it likely adds an unsupported amount or compares the wrong financial base.

Memory Technique

Collection Report money test: bucket before math for receivables aging.

Reference Hint

Open-book path: tab Builder's Guide to Accounting, 2001 to Section One, Managing Receivables, Track Your Receivables Trend; use the job ledger figures in the stem and recompute the same accounting measure.

Was this explanation helpful?

More Business & Finance Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.