EstatePass
Business & FinanceOperationsmedium10% of exam part

A Pinecrest punch list has 15 trade items estimated at $125 each. What completion cost should be forecast?

Correct Answer

B) $1,875

Punch-list completion forecast equals open item count multiplied by estimated cost per item.

Answer Options
A
$140
B
$1,875
C
$1,750
D
$2,375

Why This Is the Correct Answer

Punch-list completion forecast equals open item count multiplied by estimated cost per item.

Why the Other Options Are Wrong

Option A: $140

$140 is below the supported result for punch-list completion forecast; it likely omits allowance, conversion, coverage, or final round-up.

Option C: $1,750

$1,750 is below the supported result for punch-list completion forecast; it likely omits allowance, conversion, coverage, or final round-up.

Option D: $2,375

$2,375 is above the supported result for punch-list completion forecast; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Measure to forecast, adjust for open, then let Manager Forecasts set the finish line.

Reference Hint

Open-book path: tab Builder's Guide to Accounting, 2001 to Builder's Guide to Accounting, Job cost forecasts and completion-cost estimates; verify the trade cost, production, or field-control rule before answering.

Was this explanation helpful?

More Business & Finance Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.