EstatePass
Business & FinanceOperationsmedium10% of exam part

A Jensen Beach material line planned 620 units but used 690 units at $12 each. What cost variance should be logged?

Correct Answer

B) $840

Material cost variance equals quantity variance multiplied by unit cost.

Answer Options
A
$8,280
B
$840
C
$7,440
D
$70

Why This Is the Correct Answer

Material cost variance equals quantity variance multiplied by unit cost.

Why the Other Options Are Wrong

Option A: $8,280

$8,280 is above the supported result for material usage variance; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option C: $7,440

$7,440 is above the supported result for material usage variance; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option D: $70

$70 is below the supported result for material usage variance; it likely omits allowance, conversion, coverage, or final round-up.

Memory Technique

Cost Clerk takeoff: count the condition before counting the package.

Reference Hint

Open-book path: tab Builder's Guide to Accounting, 2001 to Builder's Guide to Accounting, Material cost variance and job cost records; verify the trade cost, production, or field-control rule before answering.

Was this explanation helpful?

More Business & Finance Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.