A Bonita Springs trade material has a 21-day lead time and must be installed on project day 35. What latest release day keeps the activity supplied?
Correct Answer
B) project day 14
Latest release day equals required install day minus procurement lead time.
Why This Is the Correct Answer
Latest release day equals required install day minus procurement lead time.
Why the Other Options Are Wrong
Option A: project day 56
project day 56 is above the supported result for procurement release timing; it likely adds scope or money the rule does not allow.
Option C: project day 21
project day 21 is above the supported result for procurement release timing; it likely adds scope or money the rule does not allow.
Option D: project day 35
project day 35 is above the supported result for procurement release timing; it likely adds scope or money the rule does not allow.
Memory Technique
Purchasing Manager contract math: approved scope is the ruler for procurement release.
Reference Hint
Open-book path: tab Contractor's Manual, 2025 to Contractor's Manual, Purchasing controls and procurement lead-time planning; verify the trade cost, production, or field-control rule before answering.
More Business & Finance Questions
The Cedar Key subcontract closeout file requires 44 final releases, and 31 have been received. How many releases are missing?
A Florida GC prepaid $18,000 for annual insurance and expenses it evenly by month. After 7 months have expired, what prepaid asset remains?
The West Miami system access list starts with 22 active users, adds 4, and removes 7. How many active users should remain?
The Winter Park bank review shows a bank balance of $124,600, book balance of $119,400, and known timing items of $3,200. What unexplained difference remains?
The Riverview bank review shows a bank balance of $87,500, book balance of $90,400, and known timing items of $1,600. What unexplained difference remains?
A Satellite Beach contractor had 4 separations during the quarter and an average headcount of 32. What turnover rate should HR report?
A Winter Park startup budgets monthly overhead of $61,500 and wants a 4-month operating reserve. What reserve should be funded?
A Royal Palm Beach customer account has unpaid approved invoices of $126,000. Company policy requires review when unpaid invoices exceed $100,000. What status applies?
A Wildwood contractor had 9 separations during the quarter and an average headcount of 60. What turnover rate should HR report?
A Clermont field group had 64 absence hours out of 1280 scheduled hours. What absence rate should be reported?
People Also Study
Related Study Resources
Previous Question
A Tampa hourly carpenter earns $31 per hour, works 40 regular hours, and works 5 overtime hours at time-and-a-half. What gross wages should be recorded?
Next Question
A Winter Haven contract price is $1,765,000 and current estimated total cost is $1,323,750. What estimated gross profit is in the WIP schedule?