A Sarasota retail build-out has a $480,000 contract. Costs incurred are $160,000, estimated cost to complete is $240,000, and billings to date are $215,000. Under percent-complete reporting, what billing position should be shown?

Correct Answer

B) $23,000 overbilled

Total estimated cost is $400,000, so the job is 40% complete. Earned revenue is $192,000, and billings of $215,000 exceed earned revenue by $23,000.

Answer Options
A
$17,000 underbilled
B
$23,000 overbilled
C
$55,000 overbilled
D
$80,000 underbilled

Why This Is the Correct Answer

Total estimated cost is $400,000, so the job is 40% complete. Earned revenue is $192,000, and billings of $215,000 exceed earned revenue by $23,000.

Why the Other Options Are Wrong

Option A: $17,000 underbilled

$17,000 underbilled is below the supported result for wip schedule over/under billing; it likely uses the wrong base, period, or account bucket.

Option C: $55,000 overbilled

$55,000 overbilled is above the supported result for wip schedule over/under billing; it likely adds an unsupported amount or compares the wrong financial base.

Option D: $80,000 underbilled

$80,000 underbilled is above the supported result for wip schedule over/under billing; it likely adds an unsupported amount or compares the wrong financial base.

Memory Technique

Reviewing Month-End money test: bucket before math for wip schedule over under.

Reference Hint

Open-book path: tab Builder's Guide to Accounting, 2001 to Section One, Accounting Methods, Percentage-of-Completion Method; Section Three, Recording Before the Event, Percentage of Completion Adjustments; use the job ledger figures in the stem and recompute the same accounting measure.

Was this explanation helpful?

More Business & Finance Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.