EstatePass
Business & FinanceAccountingmedium32% of exam part

A Hialeah progress invoice before retainage is $364,000, and the contract retains 7.5%. What net current billing should be sent?

Correct Answer

D) $336,700.00

Net current billing equals gross progress billing less retained amount.

Answer Options
A
$27,300.00
B
$364,000.00
C
$309,400.00
D
$336,700.00

Why This Is the Correct Answer

Net current billing equals gross progress billing less retained amount.

Why the Other Options Are Wrong

Option A: $27,300.00

$27,300.00 is below the supported result for progress billing retainage; it likely uses the wrong base, period, or account bucket.

Option B: $364,000.00

$364,000.00 is above the supported result for progress billing retainage; it likely adds an unsupported amount or compares the wrong financial base.

Option C: $309,400.00

$309,400.00 is below the supported result for progress billing retainage; it likely uses the wrong base, period, or account bucket.

Memory Technique

Draw Request money test: bucket before math for progress billing.

Reference Hint

Open-book path: tab Builder's Guide to Accounting, 2001 to Section One, Cash and Charge Sales, Accounts Receivable; use the job ledger figures in the stem and recompute the same accounting measure.

Was this explanation helpful?

More Business & Finance Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.