A project estimate shows total expected cost of $860,000. Cost posted to date is $301,000. What estimated cost to complete remains?

Correct Answer

B) $559,000

Cost to complete is total expected cost less cost posted to date.

Answer Options
A
$539,000
B
$559,000
C
$579,000
D
$602,000

Why This Is the Correct Answer

Cost to complete is total expected cost less cost posted to date.

Why the Other Options Are Wrong

Option A: $539,000

$539,000 is below the supported result for cost to complete; it likely uses the wrong base, period, or account bucket.

Option C: $579,000

$579,000 is above the supported result for cost to complete; it likely adds an unsupported amount or compares the wrong financial base.

Option D: $602,000

$602,000 is above the supported result for cost to complete; it likely adds an unsupported amount or compares the wrong financial base.

Memory Technique

Cost To Complete drawer for Manager Updates: label expected before counting dollars.

Reference Hint

Open-book path: tab Builder's Guide to Accounting, 2001 to Section One, Accounting Methods, Percentage-of-Completion Method; use the job ledger figures in the stem and recompute the same accounting measure.

Was this explanation helpful?

More Business & Finance Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.