EstatePass
NASCLAPlans & Specsmedium10% of exam part

During the submittal process, the architect rejects shop drawings for curtain wall systems due to inadequate structural calculations. As the general contractor, what is your next step?

Correct Answer

D) Return the shop drawings to the subcontractor for revision

When shop drawings are rejected by the architect, the general contractor should return them to the responsible subcontractor for correction and resubmission. The subcontractor is responsible for providing adequate information.

Answer Options
A
Hire an independent engineer to verify the calculations
B
Proceed with installation using similar approved details
C
Request the architect to provide the required calculations
D
Return the shop drawings to the subcontractor for revision

Why This Is the Correct Answer

When an architect rejects shop drawings, the general contractor's proper role is to route the rejected drawings back to the responsible subcontractor — in this case the curtain wall subcontractor — for correction and resubmission. The subcontractor supplied the shop drawings and bears responsibility for ensuring the structural calculations meet the specifications. The GC's duty is to manage the submittal flow, not to engineer solutions.

Why the Other Options Are Wrong

Option A: Hire an independent engineer to verify the calculations

Hiring an independent engineer to verify calculations is the subcontractor's obligation, not the GC's. The GC taking on engineering responsibility could create liability and would bypass the contractual chain of responsibility. It also does not resolve the underlying deficiency in the subcontractor's documentation.

Option B: Proceed with installation using similar approved details

Proceeding with installation using 'similar approved details' is a critical mistake. Using unapproved shop drawings bypasses the entire submittal review process, exposes the GC to liability for non-conforming work, and could result in unsafe construction that violates the contract documents.

Option C: Request the architect to provide the required calculations

Requesting the architect to provide calculations reverses the contractual responsibility. The architect's role is review and approval, not production of the contractor's or subcontractor's engineering documentation. Asking the architect to produce calculations would be inappropriate and outside the standard division of responsibility.

Memory Technique

Think of shop drawings as a package: the architect stamps 'Return to Sender' and the GC is the post office — they deliver the rejected package back to the originating subcontractor, not try to fix the contents themselves.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.