A construction project has the following costs: Direct materials $125,000, Direct labor $85,000, Equipment rental $15,000, Project management salary $12,000, and Company headquarters rent $8,000. What are the total direct costs for this project?
Correct Answer
A) $225,000
Direct costs are those directly attributable to the project: Direct materials ($125,000) + Direct labor ($85,000) + Equipment rental ($15,000) = $225,000. Project management and headquarters rent are indirect costs.
Why This Is the Correct Answer
Direct costs are those directly attributable to the project: Direct materials ($125,000) + Direct labor ($85,000) + Equipment rental ($15,000) = $225,000. Project management and headquarters rent are indirect costs.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?