During project closeout, the owner requests training for their maintenance staff on new building systems. This was not included in the original contract scope. What should the general contractor do?

Correct Answer

A) Propose a change order for the additional training services

Since training was not in the original scope, the contractor should propose a change order to provide these services, ensuring proper compensation while maintaining good client relationships.

Answer Options
A
Propose a change order for the additional training services
B
Refuse the request since it's outside the contract scope
C
Provide the training at no cost to maintain client relations
D
Have the equipment manufacturers provide training directly

Why This Is the Correct Answer

Since training was not in the original scope, the contractor should propose a change order to provide these services, ensuring proper compensation while maintaining good client relationships.

Was this explanation helpful?

More nascla-commercial-gc Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing