During contract administration, what is the proper procedure when the owner requests a change that will increase the project cost?

Correct Answer

C) Prepare a written change order for approval before proceeding

All changes that affect cost, time, or scope must be documented in writing and approved before proceeding to avoid disputes and ensure proper compensation for additional work.

Answer Options
A
Proceed with the work and bill for extra costs later
B
Make the change and absorb the costs
C
Prepare a written change order for approval before proceeding
D
Refuse the change to avoid complications

Why This Is the Correct Answer

Written change orders are legally required for any modifications that affect project cost, schedule, or scope. This protects both the contractor and owner by establishing clear documentation of approved changes before work begins. Proceeding without written approval can lead to payment disputes, legal issues, and potential losses for the contractor. The change order process ensures all parties understand and agree to the modifications and associated costs upfront.

Why the Other Options Are Wrong

Option A: Proceed with the work and bill for extra costs later

Refusing changes unnecessarily damages client relationships and may violate contractual obligations to consider reasonable modifications

Option D: Refuse the change to avoid complications

Proceeding without written approval creates significant risk of non-payment and disputes, as there's no documented agreement for the extra work and costs

Memory Technique

Use the acronym 'WAP' - Written Approval first, then Proceed with work

Reference Hint

Florida Building Code - Chapter 1, Section 105 (Permits and Inspections) and AIA Contract Documents regarding change order procedures

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.