EstatePass
Business & FinanceAdminmedium26% of exam part

During contract administration, a change order is requested that will extend the project schedule by 15 days. What documentation should be prepared along with the change order?

Correct Answer

C) Cost impact and schedule analysis with time extension request

Change orders affecting both cost and schedule require comprehensive documentation including cost analysis and schedule impact assessment with formal time extension request. This ensures all impacts are properly documented and approved.

Answer Options
A
Updated insurance certificates for the extended period
B
New project schedule showing the revised completion date
C
Cost impact and schedule analysis with time extension request
D
Only the cost impact analysis

Why This Is the Correct Answer

Option B is correct because when a change order affects both project cost and schedule, comprehensive documentation is required to properly evaluate and approve the change. The cost impact analysis quantifies the financial implications, while the schedule analysis demonstrates how the change affects the project timeline. The formal time extension request provides the contractual mechanism to adjust the completion date. This complete documentation package ensures all stakeholders understand the full impact and can make informed decisions.

Why the Other Options Are Wrong

Option A: Updated insurance certificates for the extended period

Option A is incomplete because it only addresses the cost impact while ignoring the schedule implications. Since the question specifically mentions a 15-day schedule extension, failing to include schedule analysis and time extension documentation would leave the change order incomplete and potentially unenforceable.

Option D: Only the cost impact analysis

Option D focuses on insurance requirements which, while potentially necessary for extended projects, is not the primary documentation needed for change order approval. This option misses the critical cost and schedule analysis components that are essential for proper change order processing.

Memory Technique

Use 'C.S.T.' - Cost, Schedule, Time extension - all three must be documented when a change order affects the timeline

Reference Hint

Florida Building Code Chapter 1, Section 105 - Construction Documents and Chapter 4 - Special Detailed Requirements for construction administration

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.