EstatePass
NASCLAContractseasy15% of exam part

During construction, the owner requests additional work that was not included in the original contract scope. What document should the contractor prepare to formalize this change?

Correct Answer

B) Change Order Request

A Change Order Request is the proper document to propose changes to the contract scope, time, or price for owner-requested additional work.

Answer Options
A
Payment Application
B
Change Order Request
C
Request for Information (RFI)
D
Field Work Order

Why This Is the Correct Answer

A Change Order Request is the correct document when the owner requests work outside the original contract scope. It formally proposes modifications to the contract's scope of work, schedule, and/or price, creating a documented paper trail and requiring owner approval before the extra work begins.

Why the Other Options Are Wrong

Option A: Payment Application

A Payment Application is used to request payment for work already completed under the existing contract β€” it does not modify or expand the contract scope.

Option C: Request for Information (RFI)

A Request for Information (RFI) is used to seek clarification on ambiguous or incomplete contract documents. It asks a question; it does not authorize or formalize new work.

Option D: Field Work Order

A Field Work Order is an internal document used to direct field crews on task assignments. It is not the formal contract instrument used to document owner-requested scope changes.

Memory Technique

Think 'COR = Change Order = Contract is Ordered to change.' Any time the owner asks for something new or different, the contractor must protect themselves with a signed Change Order before proceeding.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.