During construction, the electrical subcontractor submits shop drawings showing a deviation from the contract documents. As the general contractor, what is your primary responsibility?

Correct Answer

D) Forward to the architect/engineer for review

Shop drawings must be reviewed by the design professional (architect/engineer) for compliance with design intent. The general contractor's role is to review for coordination and forward to the appropriate party.

Answer Options
A
Approve the deviation if it meets code
B
Implement the change and notify the owner
C
Reject the deviation immediately
D
Forward to the architect/engineer for review

Why This Is the Correct Answer

Shop drawings must be reviewed by the design professional (architect/engineer) for compliance with design intent. The general contractor's role is to review for coordination and forward to the appropriate party.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.