During bid preparation, a major subcontractor withdraws their quote 30 minutes before bid submission. The next lowest quote is $25,000 higher. What is the most appropriate action?

Correct Answer

A) Submit the bid using the higher quote

The contractor must submit a bid based on available, valid quotes. Using a withdrawn quote would be unethical and could lead to financial loss. The bid should include the higher quote to ensure accuracy.

Answer Options
A
Submit the bid using the higher quote
B
Withdraw from the bidding process
C
Submit the bid using the original lower quote
D
Submit the bid with a qualification noting the substitution

Why This Is the Correct Answer

The contractor must submit a bid based on available, valid quotes. Using a withdrawn quote would be unethical and could lead to financial loss. The bid should include the higher quote to ensure accuracy.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.