EstatePass
Business & FinanceAdminmedium26% of exam part

During bid preparation, a contractor discovers a significant discrepancy between the plans and specifications. What is the most appropriate course of action?

Correct Answer

C) Submit a Request for Information (RFI) to clarify the discrepancy

When discrepancies exist between plans and specifications, the proper procedure is to submit an RFI to the owner or architect for clarification. This ensures accurate bidding and prevents disputes during construction.

Answer Options
A
Submit the bid based on the plans only
B
Include an allowance in the bid to cover potential issues
C
Submit a Request for Information (RFI) to clarify the discrepancy
D
Submit the bid based on the specifications only

Why This Is the Correct Answer

Submitting an RFI (Request for Information) is the proper professional procedure when discrepancies exist between plans and specifications during bid preparation. This formal process ensures all bidders receive the same clarification, maintains fairness in the bidding process, and prevents costly disputes or change orders during construction. The RFI allows the design team to provide official clarification that becomes part of the contract documents.

Why the Other Options Are Wrong

Option A: Submit the bid based on the plans only

Including an allowance without seeking clarification is unprofessional and risky, as it doesn't resolve the actual discrepancy and may result in an uncompetitive bid or insufficient funds to cover the actual requirements once the discrepancy is resolved.

Option B: Include an allowance in the bid to cover potential issues

Submitting a bid based only on the specifications while ignoring conflicting plans is equally problematic, as both documents are typically part of the contract and the contractor would be obligated to follow both, creating potential conflicts during construction.

Memory Technique

Think 'RFI before you FLY' - always Request For Information before you submit your bid when there are discrepancies

Reference Hint

Florida Building Code Administration chapter or AIA General Conditions sections dealing with contract document interpretation and RFI procedures

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.