During a project, the owner requests a change order that will add $50,000 to the contract value. The contractor's standard markup is 15% for overhead and profit. What should be the total change order amount?
Correct Answer
C) $57,500
The change order should include the contractor's standard markup for overhead and profit. $50,000 × 15% = $7,500 markup. Total change order = $50,000 + $7,500 = $57,500.
Why This Is the Correct Answer
When calculating change orders, contractors must add their standard markup for overhead and profit to the base cost. The $50,000 represents the direct cost of the additional work. With a 15% markup: $50,000 × 0.15 = $7,500 markup. The total change order amount becomes $50,000 + $7,500 = $57,500. This ensures the contractor maintains profitability on change work consistent with their original contract terms.
Why the Other Options Are Wrong
Option A: $52,500
$52,500 represents only a 5% markup ($50,000 × 0.05 = $2,500), which is significantly below the contractor's standard 15% markup rate. This would result in inadequate compensation for overhead and profit on the change order work.
Option B: $60,000
$60,000 represents a 20% markup ($10,000 ÷ $50,000 = 20%), which exceeds the contractor's standard 15% markup rate. While this might seem favorable to the contractor, it's inconsistent with established contract terms and could create disputes.
Option D: $50,000
$50,000 represents only the base cost without any markup for overhead and profit. This would mean the contractor performs additional work without compensation for business expenses and profit, which is financially unsustainable.
Memory Technique
Remember 'Change + Charge': Change orders need the contractor's standard markup charge added to maintain profit margins, just like the original contract.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
