EstatePass
nascla-commercial-gcProject Managementmedium

During a pre-construction meeting, the electrical subcontractor requests to start rough-in work before the framing is complete. As the general contractor, what is the most appropriate response?

Correct Answer

D) Deny the request and refer to the project schedule dependencies

Electrical rough-in typically depends on framing completion for proper installation. The GC should maintain schedule logic and safety by following proper sequencing.

Answer Options
A
Approve only if the electrical contractor assumes liability
B
Approve the request to accelerate the schedule
C
Require written approval from the owner first
D
Deny the request and refer to the project schedule dependencies

Why This Is the Correct Answer

Electrical rough-in typically depends on framing completion for proper installation. The GC should maintain schedule logic and safety by following proper sequencing.

Was this explanation helpful?

More nascla-commercial-gc Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing