EstatePass
Project MgmtConstructionmedium63% of exam part

During a cut and fill operation, the contractor discovers that 1,200 cubic yards of soil must be moved from the cut area to the fill area. If the soil has a swell factor of 25%, how many cubic yards will need to be hauled?

Correct Answer

C) 1,500 cubic yards

When soil is excavated, it swells due to loosening. With a 25% swell factor, the volume increases by 25%. Therefore, 1,200 cubic yards × 1.25 = 1,500 cubic yards will need to be hauled.

Answer Options
A
1,200 cubic yards
B
1,800 cubic yards
C
1,500 cubic yards
D
960 cubic yards

Why This Is the Correct Answer

Option C is correct because when soil is excavated from its natural state, it expands or 'swells' due to the loosening of particles and increased air voids. The 25% swell factor means the volume increases by 25% from its original in-place volume. To calculate the hauled volume, you multiply the in-place volume by (1 + swell factor percentage), which gives 1,200 × 1.25 = 1,500 cubic yards. This represents the actual volume that trucks will need to transport from the cut to fill areas.

Why the Other Options Are Wrong

Option A: 1,200 cubic yards

Option A incorrectly applies shrinkage instead of swell, calculating 1,200 ÷ 1.25 = 960 cubic yards, which would be the compacted volume rather than the loose hauled volume.

Option B: 1,800 cubic yards

Option D incorrectly calculates 1,200 × 1.5 = 1,800 cubic yards, which would represent a 50% swell factor rather than the given 25% swell factor.

Option D: 960 cubic yards

Option B ignores the swell factor entirely, assuming the hauled volume equals the in-place volume, which is incorrect since excavated soil always increases in volume when disturbed.

Memory Technique

Remember 'SWELL = SELL MORE' - when soil swells, you need to haul MORE volume than what was originally in place, so always multiply by a number greater than 1.

Reference Hint

Look up 'Earthwork and Excavation' or 'Soil Volume Changes' in construction management references, typically found in site work or earthwork chapters.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.