During a confined space entry, the atmospheric testing reveals 19.2% oxygen, 0% LEL, and 8 ppm hydrogen sulfide. Based on these readings, what action should be taken?
Correct Answer
A) Entry prohibited - oxygen deficient atmosphere
OSHA requires oxygen levels between 19.5% and 23.5% for safe entry. At 19.2%, this is an oxygen-deficient atmosphere and entry is prohibited until corrected.
Why This Is the Correct Answer
OSHA requires oxygen levels between 19.5% and 23.5% for safe entry. At 19.2%, this is an oxygen-deficient atmosphere and entry is prohibited until corrected.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A cost-plus contract has actual costs of $1,850,000 with a contractor fee of 6%. Additional costs due to owner-directed changes total $125,000. What is the total amount due to the contractor?
Next Question
Which insurance coverage would protect a contractor against claims arising from faulty workmanship that causes property damage after project completion?