During a concrete pour for a commercial foundation, the ready-mix truck is delayed and concrete begins to stiffen before placement is complete. What is the most appropriate action?
Correct Answer
C) Reject the concrete if initial set has begun
Once concrete begins initial set, it should be rejected. Adding water compromises strength, and excessive vibration won't restore workability of setting concrete.
Why This Is the Correct Answer
Once concrete begins initial set, it should be rejected. Adding water compromises strength, and excessive vibration won't restore workability of setting concrete.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor expects to receive $400,000 in payments next month but must pay $520,000 in expenses. The current cash balance is $75,000. What action should the contractor take?
Next Question
A contractor receives shop drawings for structural steel that show connections different from the original design drawings. What is the appropriate next step?
