A contractor expects to receive $400,000 in payments next month but must pay $520,000 in expenses. The current cash balance is $75,000. What action should the contractor take?
Correct Answer
B) Arrange for additional financing of at least $45,000
Projected cash shortage = $75,000 + $400,000 - $520,000 = -$45,000. The contractor needs at least $45,000 in additional financing to cover the shortfall.
Why This Is the Correct Answer
Projected cash shortage = $75,000 + $400,000 - $520,000 = -$45,000. The contractor needs at least $45,000 in additional financing to cover the shortfall.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor needs a crane for 6 weeks. The rental cost is $1,800 per week plus $150 per day for an operator. If purchasing, the crane costs $85,000 with $12,000 annual maintenance and a 10-year depreciation. The operator cost remains the same. Assuming 5 working days per week, what is the cost difference between renting and the allocated purchase cost?
Next Question
During a concrete pour for a commercial foundation, the ready-mix truck is delayed and concrete begins to stiffen before placement is complete. What is the most appropriate action?