Calculate the volume of concrete needed for a rectangular foundation wall that is 100 feet long, 8 inches thick, and 8 feet high.

Correct Answer

A) 19.8 cubic yards

Volume = 100 ft × 0.67 ft (8 inches) × 8 ft = 533.3 cubic feet. Converting to cubic yards: 533.3 ÷ 27 = 19.8 cubic yards.

Answer Options
A
19.8 cubic yards
B
23.7 cubic yards
C
21.2 cubic yards
D
18.5 cubic yards

Why This Is the Correct Answer

Option B is correct because it properly converts all measurements to the same units (feet), calculates the volume in cubic feet, and then converts to cubic yards. The calculation follows the standard formula: Volume = Length × Width × Height, where 8 inches is correctly converted to 0.67 feet (8÷12). The final step divides by 27 to convert cubic feet to cubic yards, yielding 19.8 cubic yards.

Why the Other Options Are Wrong

Option B: 23.7 cubic yards

This answer is too low, likely resulting from an error in unit conversion or calculation. It may have used an incorrect conversion factor or made an arithmetic mistake in the division.

Option D: 18.5 cubic yards

This answer is too high, possibly from using incorrect units or failing to properly convert inches to feet. It might result from using 8 inches as 0.8 feet instead of the correct 0.67 feet.

Memory Technique

Remember '27 to fly' - there are 27 cubic feet in 1 cubic yard (3×3×3=27). Also remember '12 inches per foot' for conversions.

Reference Hint

Look up concrete volume calculations in Chapter 3 (Materials and Methods) or the concrete/masonry section of your contractor reference manual.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.