EstatePass
NASCLAConstructionmedium5% of exam part

An excavation project requires removing 15,000 cubic yards of soil. If the soil has a swell factor of 25%, how many cubic yards of soil must be hauled away?

Correct Answer

C) 18,750 cubic yards

With a 25% swell factor, the soil volume increases when excavated. Volume to haul = 15,000 cu yd × 1.25 = 18,750 cubic yards.

Answer Options
A
20,000 cubic yards
B
15,000 cubic yards
C
18,750 cubic yards
D
12,000 cubic yards

Why This Is the Correct Answer

With a 25% swell factor, the soil volume increases when excavated. Volume to haul = 15,000 cu yd × 1.25 = 18,750 cubic yards.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing