EstatePass
NASCLAEstimatingmedium18% of exam part

According to standard bidding practices, when should a general contractor typically submit requests for clarification on bid documents?

Correct Answer

C) Within the timeframe specified in the instructions to bidders

Bid documents typically specify a deadline for questions and clarifications, usually 5-7 days before bid submission, to allow time for responses to reach all bidders.

Answer Options
A
Only during the pre-bid conference
B
At any time before bid opening
C
Within the timeframe specified in the instructions to bidders
D
At least 48 hours before bid submission

Why This Is the Correct Answer

Bid documents always include an 'Instructions to Bidders' section that specifies a deadline for questions and clarification requests. Submitting questions within this window ensures all bidders receive the same addendum response, maintaining fairness and completeness.

Why the Other Options Are Wrong

Option A: Only during the pre-bid conference

Questions are not restricted to the pre-bid conference only. While conferences are one opportunity to ask questions, the Instructions to Bidders typically allow written RFIs up to a specified cutoff date.

Option B: At any time before bid opening

'At any time before bid opening' ignores the specified deadline. Late questions may not receive an answer, and responses issued too close to bid opening may not allow all bidders adequate time to revise their estimates.

Option D: At least 48 hours before bid submission

48 hours is a commonly assumed rule of thumb but is not the universal standard. The actual deadline is whatever the Instructions to Bidders specifies, which is often 5–7 days before bid submission.

Memory Technique

RFI = 'Read the Instructions First.' The Instructions to Bidders always contain the deadline β€” read that section before preparing any questions.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing