A subcontractor submits a Request for Information (RFI) about conflicting dimensions on structural drawings. The project is on a tight schedule. What is the proper sequence of actions?
Correct Answer
B) Forward RFI to architect, track response time, communicate resolution to affected parties
RFIs must follow proper channels through the architect/engineer for technical resolution, with proper documentation and communication to all affected parties to maintain project coordination.
Why This Is the Correct Answer
RFIs must follow proper channels through the architect/engineer for technical resolution, with proper documentation and communication to all affected parties to maintain project coordination.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
What is the primary purpose of a vapor retarder in a commercial roofing system?
Next Question
A punch list contains 45 items total: 12 major items and 33 minor items. The contract allows substantial completion when minor items only remain. How many items must be completed before substantial completion?