A subcontractor submits a payment application for $85,000. The contract specifies 10% retention until project completion. What amount should be paid?
Correct Answer
A) $76,500
With 10% retention, the payment amount = $85,000 × (100% - 10%) = $85,000 × 0.90 = $76,500. The $8,500 retention will be held until project completion.
Why This Is the Correct Answer
Option A is correct because retention calculations require multiplying the payment application amount by the percentage that will be paid (not retained). With 10% retention, 90% is paid immediately. The calculation is $85,000 × 0.90 = $76,500. The remaining $8,500 (10%) is held as retention until project completion or final acceptance.
Why the Other Options Are Wrong
Option C: $80,000
This amount doesn't correspond to any standard retention calculation and appears to be an arbitrary figure that doesn't follow the 10% retention requirement.
Option D: $78,000
This represents paying the full amount without any retention deduction, which violates the contract terms specifying 10% retention until completion.
Memory Technique
Remember 'R.P.M.' - Retention Percentage Minus (from 100%) = Payment percentage. Then multiply the application amount by the payment percentage.
Reference Hint
Florida Building Code Chapter 1, Section 107 - Fees and Permits, or contract administration sections in general contracting reference materials
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
