A subcontractor submits a bid of $125,000 for electrical work but has a history of 15% cost overruns. If you include a 10% contingency for this trade, what amount should you include in your estimate?
Correct Answer
B) $143,750
Base bid with typical overrun: $125,000 × 1.15 = $143,750. Since you're already accounting for the subcontractor's history of overruns, the 10% contingency would be redundant and not added again.
Why This Is the Correct Answer
The correct approach is to apply the subcontractor's known 15% cost overrun history to the base bid: $125,000 × 1.15 = $143,750. Because this calculation already incorporates the historical overrun pattern, adding a separate 10% contingency on top would double-count the risk for the same underlying issue. The 10% contingency is intended for unknown risks, not for known patterns already reflected in the adjusted estimate. This principle — avoiding redundant contingency — is central to accurate estimating.
Why the Other Options Are Wrong
Option A: $156,250
$156,250 results from applying both the 15% overrun AND the 10% contingency ($125,000 × 1.15 × 1.10 = $156,250). This double-counts the risk since the 15% adjustment already accounts for the subcontractor's history. A contingency should only cover unknown risks, not patterns already quantified.
Option C: $137,500
$137,500 applies only a 10% contingency to the base bid ($125,000 × 1.10) while ignoring the known 15% historical overrun entirely. This underestimates the true expected cost and fails to account for documented performance history.
Option D: $158,125
$158,125 does not correspond to any standard calculation method. It appears to combine figures inconsistently. Estimates must follow a logical, reproducible methodology — applying the known overrun factor once to the base bid is the correct and defensible approach.
Memory Technique
Think 'ONE fix for ONE known problem': the 15% history IS the fix. Don't fix it twice.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Which line type is typically used on architectural drawings to represent hidden or concealed elements?
Next Question
A contractor is analyzing a potential project with an initial investment of $500,000, expected annual cash flows of $150,000 for 5 years, and a required return rate of 12%. The project should be:
