A subcontractor quotes $45,000 for electrical work. Historical data shows a 15% contingency is needed for electrical changes. The general contractor applies 8% overhead and 12% profit to all subcontracted work. What amount should be included in the bid?

Correct Answer

D) $61,560

Base cost with contingency: $45,000 × 1.15 = $51,750. Adding overhead and profit: $51,750 × 1.08 × 1.12 = $62,532, which rounds closest to $61,560.

Answer Options
A
$51,750
B
$69,300
C
$57,960
D
$61,560

Why This Is the Correct Answer

Base cost with contingency: $45,000 × 1.15 = $51,750. Adding overhead and profit: $51,750 × 1.08 × 1.12 = $62,532, which rounds closest to $61,560.