A subcontractor performed $15,000 worth of electrical work but was not paid by the general contractor. If the subcontractor files a mechanics lien and the property sells, what is their priority position for payment?
Correct Answer
C) First, ahead of mortgage holders
Alabama mechanics liens have priority over most other claims, including mortgage holders, provided they are properly filed and perfected.
Why This Is the Correct Answer
Alabama mechanics liens have priority over most other claims, including mortgage holders, provided they are properly filed and perfected.
More al-supplement Questions
An Alabama licensed contractor is required to complete continuing education. How many hours are required for license renewal?
According to Alabama building codes, what is the maximum allowable deflection for floor joists under live load?
Which continuing education topic is mandatory for Alabama contractor license renewal?
Under Alabama building codes, which edition of the International Building Code (IBC) is currently adopted?
Under Alabama law, what is the statute of limitations for filing a breach of contract claim against a contractor?
A homeowner hires you for a $25,000 kitchen renovation but refuses to pay the final $5,000. You properly file a mechanics' lien. The homeowner wants to sell the house. What happens to your lien?
Which continuing education topic is specifically mandated by Alabama for contractor license renewal?
A contractor discovers that their Alabama contractor license expired 45 days ago. What is the consequence under Title 34-8?
Your client wants to add a 500 sq ft addition to their home. You discover during construction that the existing electrical system doesn't meet current Alabama electrical code. What is your obligation?
A contractor is building a residential foundation in Alabama clay soil. The soil report indicates expansive clay with a plasticity index of 35. What is the minimum recommended foundation depth?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A material supplier files a mechanic's lien 95 days after last furnishing materials. The project was substantially complete 85 days ago. Is this lien valid under Alabama law?
Next Question
A contractor fails to complete 4 hours of required continuing education. What penalty applies under Alabama law?