GeorgiaGA Supplementmedium100% of exam part

A subcontractor in Georgia must file a Notice to Owner within how many days of first furnishing labor or materials to preserve lien rights?

Correct Answer

B) 30 days

Under O.C.G.A. § 44-14-361.1, subcontractors must file a Notice to Owner within 30 days of first furnishing labor or materials to preserve lien rights.

Answer Options
A
15 days
B
30 days
C
20 days
D
45 days

Why This Is the Correct Answer

Under O.C.G.A. § 44-14-361.1, a subcontractor or materialman who does not have a direct contract with the property owner must file a Preliminary Notice to Owner (also called a Notice to Contractor/Owner) within 30 days of first furnishing labor or materials. Missing this deadline forfeits lien rights.

Why the Other Options Are Wrong

Option A: 15 days

15 days is not the correct deadline under Georgia lien law for subcontractors. This figure does not correspond to any standard notice requirement in the Georgia mechanics lien statutes.

Option C: 20 days

20 days is not the correct Georgia deadline. This figure may be confused with notice periods in other states or other Georgia construction law provisions, but it is not the subcontractor notice-to-owner deadline.

Option D: 45 days

45 days is too long — waiting 45 days would cause the subcontractor to miss the 30-day window and lose lien rights. This timeline may be confused with the lien filing deadline after project completion, which is a separate and longer period.

Memory Technique

Georgia subcontractor notice rule: '30 days from day one.' The clock starts the moment you first show up with materials or labor. Count 30 days — that's your notice deadline. '30 from first' is the key phrase.

Was this explanation helpful?

More Georgia Questions

A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?

A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?

Which situation would require a Georgia contractor to obtain workers' compensation insurance?

A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?

A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?

A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?

A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?

A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?

A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?

What is the threshold amount above which a contractor must be licensed in Georgia?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.