A subcontractor coordination meeting reveals that the HVAC rough-in is 2 days behind schedule, which will delay the drywall installation. The project manager needs to communicate this to stakeholders. What information should be included in the communication?

Correct Answer

B) The delay cause, impact on downstream activities, and proposed recovery plan

Effective project communication should include the problem, its impact on the project, and proposed solutions. This gives stakeholders complete information to make informed decisions.

Answer Options
A
The personal details of why the HVAC crew was absent
B
The delay cause, impact on downstream activities, and proposed recovery plan
C
A recommendation to change subcontractors immediately
D
Only the fact that HVAC is delayed

Why This Is the Correct Answer

Effective project communication should include the problem, its impact on the project, and proposed solutions. This gives stakeholders complete information to make informed decisions.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.