A contractor receives shop drawings that conflict with the architectural plans. What is the proper procedure?
Correct Answer
D) Submit an RFI to the architect for clarification
When conflicts exist between documents, the contractor should submit a Request for Information (RFI) to get official clarification from the design team rather than making assumptions.
Why This Is the Correct Answer
When conflicts exist between documents, the contractor should submit a Request for Information (RFI) to get official clarification from the design team rather than making assumptions.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During a workplace inspection, you discover that Safety Data Sheets (SDS) are not readily accessible to employees. This violates which OSHA standard?
Next Question
A subcontractor coordination meeting reveals that the HVAC rough-in is 2 days behind schedule, which will delay the drywall installation. The project manager needs to communicate this to stakeholders. What information should be included in the communication?
