A subcontractor completes work valued at $8,500 on March 15th and is not paid. Under Alabama lien law, what is the last day they can file a mechanics' lien?

Correct Answer

D) July 14th

Alabama lien law requires mechanics' liens to be filed within 120 days of completion of work. 120 days from March 15th is July 14th.

Answer Options
A
May 14th
B
June 14th
C
September 14th
D
July 14th

Why This Is the Correct Answer

Alabama lien law requires a mechanics' lien to be filed within 120 days of the last day work was performed. Counting 120 days from March 15th: March has 16 remaining days (15th to 31st), April has 30 days, May has 31 days, June has 30 days, and July 13 days — totaling 120 days, landing on July 14th.

Why the Other Options Are Wrong

Option A: May 14th

May 14th is approximately 60 days from March 15th, which corresponds to a 60-day lien filing period. Alabama's mechanics' lien window is 120 days, not 60 days.

Option B: June 14th

June 14th is approximately 90 days from March 15th, reflecting a 90-day period. While 90 days is a common timeframe in contractor law for other purposes, Alabama's mechanics' lien deadline is 120 days.

Option C: September 14th

September 14th is approximately 183 days from March 15th, which exceeds Alabama's 120-day limit. Filing a lien this late would be outside the statutory window and the lien would be invalid.

Memory Technique

120 days = 4 months. March 15th + 4 months = July 15th, but since we're counting 120 actual days (not calendar months), the result lands on July 14th. When in doubt, count: 16 (March) + 30 (April) + 31 (May) + 30 (June) + 13 (July) = 120.

Was this explanation helpful?

More Alabama Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.