EstatePass
GeorgiaGA Supplementmedium100% of exam part

A subcontractor completes work on March 15th but is not paid by the general contractor. Under Georgia lien law, what is the latest date the subcontractor can file a lien claim?

Correct Answer

D) June 13th

Georgia allows 90 days from the completion of work to file a lien claim. From March 15th, 90 days later would be June 13th.

Answer Options
A
July 14th
B
May 14th
C
April 14th
D
June 13th

Why This Is the Correct Answer

Georgia's lien statute provides subcontractors 90 days from completion of work to file a lien. Counting 90 days from March 15th: 16 remaining days in March + 30 in April + 31 in May + 13 in June = 90 days total, landing on June 13th. This deadline is firm — missing it forfeits lien rights.

Why the Other Options Are Wrong

Option A: July 14th

July 14th is 121 days after March 15th — far beyond the 90-day statutory window. There is no provision in Georgia law that extends the lien filing period to four months.

Option B: May 14th

May 14th is only 60 days from March 15th. While some states use a 60-day lien period, Georgia's statute grants 90 days. Selecting this option reflects knowledge of a different state's rules.

Option C: April 14th

April 14th is only 30 days after March 15th — half the correct deadline. This may result from confusing the lien filing period with a notice or demand letter requirement, or from applying a 30-day rule from another context.

Memory Technique

Remember: GA lien = 90 days from completion. To count from March 15: days left in March = 31 - 15 = 16; April = 30 (total 46); May = 31 (total 77); need 13 more in June → June 13.

Was this explanation helpful?

More Georgia Questions

A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?

A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?

Which situation would require a Georgia contractor to obtain workers' compensation insurance?

A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?

A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?

A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?

A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?

A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?

A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?

What is the threshold amount above which a contractor must be licensed in Georgia?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.