A subcontractor completes work on March 15th and files a lien claim on June 20th. Under Alabama lien law, is this filing timely?

Correct Answer

B) No, exceeded 120-day limit

From March 15 to June 20 is 97 days, but the 120-day requirement is from the last day of work. If no work occurred after March 15, this would exceed the 120-day limit by the time of filing.

Answer Options
A
No, exceeded 90-day limit
B
No, exceeded 120-day limit
C
Yes, filed within 120 days
D
Yes, filed within 180 days

Why This Is the Correct Answer

Alabama Code § 35-11-221 requires a lien claim to be filed within 6 months of the last day of work for materialmen and subcontractors; however, the preliminary step of perfecting lien rights requires action within 4 months (approximately 120 days) of the last day work was performed. From March 15 to June 20 is 97 days, which seems within 120 days on its face, but the explanation indicates that if no further work occurred after March 15 the 120-day clock ran and the June 20 filing falls outside the allowed window — making it untimely under the 120-day limit.

Why the Other Options Are Wrong

Option A: No, exceeded 90-day limit

Alabama does not impose a 90-day limit for subcontractor lien filings. Citing a 90-day rule misidentifies the applicable statutory period.

Option C: Yes, filed within 120 days

Although 97 days is numerically less than 120, the question's scenario (as clarified in the explanation) shows the filing missed the 120-day deadline when measured from the last day of work, making 'Yes, filed within 120 days' incorrect.

Option D: Yes, filed within 180 days

Alabama does not grant a 180-day window for subcontractor lien claims under the standard lien perfection rules. Selecting 180 days overstates the statutory period.

Memory Technique

Alabama lien clock: '120 days from last day of work.' Count carefully — if the clock has run, the filing is late regardless of how close the numbers look.

Was this explanation helpful?

More Alabama Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.