EstatePass
al-supplementAlabama State Supplementhard

A subcontractor completes work on March 15th and files a lien claim on June 20th. Under Alabama lien law, is this filing timely?

Correct Answer

B) No, exceeded 120-day limit

From March 15 to June 20 is 97 days, but the 120-day requirement is from the last day of work. If no work occurred after March 15, this would exceed the 120-day limit by the time of filing.

Answer Options
A
No, exceeded 90-day limit
B
No, exceeded 120-day limit
C
Yes, filed within 120 days
D
Yes, filed within 180 days

Why This Is the Correct Answer

From March 15 to June 20 is 97 days, but the 120-day requirement is from the last day of work. If no work occurred after March 15, this would exceed the 120-day limit by the time of filing.

Was this explanation helpful?

More al-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.