GeorgiaGA Supplementmedium100% of exam part

A subcontractor completes $15,000 worth of electrical work on a residential project in Georgia. The general contractor fails to pay. Within how many days must the subcontractor serve a Notice to Owner to preserve lien rights?

Correct Answer

A) 90 days

Under Georgia lien law, subcontractors must serve a Notice to Owner within 90 days of first furnishing labor or materials to preserve their lien rights.

Answer Options
A
90 days
B
120 days
C
60 days
D
30 days

Why This Is the Correct Answer

Under Georgia's lien statute (O.C.G.A. § 44-14-361.5), subcontractors and suppliers who do not have a direct contract with the property owner must serve a written Notice to Owner (also called a preliminary notice) within 90 days of first furnishing labor or materials on the project. This notice is a prerequisite to filing a valid lien — without it, the subcontractor loses lien rights entirely.

Why the Other Options Are Wrong

Option B: 120 days

120 days exceeds Georgia's statutory deadline for serving a Notice to Owner. A subcontractor who waits 120 days will have already missed the 90-day window and will have forfeited their lien rights. This is a critical timing error that cannot be undone.

Option C: 60 days

60 days is shorter than Georgia's actual 90-day deadline. While serving notice earlier is always advisable, the statutory maximum is 90 days — not 60. A subcontractor who knows this correctly has up to 90 days to serve the notice, though waiting until day 90 is risky.

Option D: 30 days

30 days is far too short. No Georgia statute requires the Notice to Owner within 30 days of first furnishing. This may reflect confusion with other notice periods (such as stop-payment notices or notice periods in other states), but Georgia's lien law provides 90 days for this notice.

Memory Technique

In Georgia, the number 90 is king for lien notices: '90 days to notice, 90 days to lien.' Both the Notice to Owner deadline (from first furnishing) and the lien filing deadline (from last furnishing/completion) involve 90-day windows. If you remember '90 for Georgia liens,' you cover both steps.

Was this explanation helpful?

More Georgia Questions

A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?

A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?

Which situation would require a Georgia contractor to obtain workers' compensation insurance?

A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?

A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?

A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?

A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?

A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?

A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?

What is the threshold amount above which a contractor must be licensed in Georgia?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.