A subcontractor begins work on March 15th and completes work on May 20th. Payment is due June 1st but not received. Under Alabama lien law, what is the last day to file a lien claim?

Correct Answer

C) November 20th

Alabama lien law requires filing within 6 months of completion of work. Six months from May 20th is November 20th.

Answer Options
A
August 20th
B
December 1st
C
November 20th
D
September 1st

Why This Is the Correct Answer

Alabama lien law requires filing within 6 months of completion of work. Six months from May 20th is November 20th.

Was this explanation helpful?

More al-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.