A subcontractor begins work on January 15th and completes work on March 10th. The general contractor receives final payment on April 5th. Under Georgia prompt payment law, when must the subcontractor be paid?

Correct Answer

C) April 19th

Georgia prompt payment law requires payment to subcontractors within 14 days after the general contractor receives payment. April 5th + 14 days = April 19th.

Answer Options
A
April 12th
B
May 5th
C
April 19th
D
March 17th

Why This Is the Correct Answer

Georgia's Prompt Payment Act requires that once a general contractor receives payment from the owner, the subcontractor must be paid within 14 days. The general contractor received payment on April 5th. Adding 14 days: April 5 + 14 days = April 19th. The work start and completion dates are provided as distractors — the 14-day clock starts when the general contractor receives payment, not when the subcontractor finishes work.

Why the Other Options Are Wrong

Option A: April 12th

April 12th would result from adding only 7 days to April 5th. Georgia's prompt payment requirement is 14 days after the general contractor receives payment, not 7 days.

Option B: May 5th

May 5th would result from adding 30 days to April 5th, or from miscalculating based on a monthly payment cycle. Georgia law requires payment within 14 days, not 30 days.

Option D: March 17th

March 17th is 7 days after the subcontractor's completion date of March 10th. This is incorrect because the 14-day clock under Georgia's Prompt Payment Act does not start at subcontractor completion — it starts when the general contractor receives payment from the owner (April 5th).

Memory Technique

Georgia Prompt Payment = 'GC gets paid → 14 days → Sub gets paid.' Ignore all other dates. Find when the GC received payment, add 14 days.

Was this explanation helpful?

More Georgia Questions

A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?

A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?

Which situation would require a Georgia contractor to obtain workers' compensation insurance?

A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?

A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?

A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?

A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?

A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?

A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?

What is the threshold amount above which a contractor must be licensed in Georgia?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.