A subcontract agreement includes a pay-when-paid clause. The owner becomes insolvent and cannot pay the general contractor. What is the subcontractor's legal position?
Correct Answer
B) The pay-when-paid clause becomes void due to impossibility
Courts often find pay-when-paid clauses unenforceable when payment becomes impossible due to owner insolvency.
Why This Is the Correct Answer
Courts generally treat pay-when-paid clauses as timing mechanisms, not as risk-shifting devices that permanently eliminate the subcontractor's right to payment. When owner insolvency makes payment impossible, courts frequently hold that the condition (receipt of owner payment) cannot be fulfilled, making the clause void under the doctrine of impossibility. The subcontractor retains the right to seek payment from the general contractor.
Why the Other Options Are Wrong
Option A: The subcontractor can demand immediate payment from the general contractor
While the subcontractor may ultimately have the right to payment, demanding 'immediate' payment without legal process overstates the subcontractor's position. The legal path requires demonstrating that the pay-when-paid condition has been voided by impossibility β it is not an automatic trigger for immediate collection.
Option C: The subcontractor can only seek payment from the payment bond
Limiting the subcontractor to payment bond claims only is too narrow. A payment bond is one avenue of recovery, but it is not the exclusive remedy when a pay-when-paid clause is voided. The subcontractor may pursue the general contractor directly once impossibility voids the condition.
Option D: The subcontractor must wait indefinitely for payment
Requiring indefinite waiting would effectively convert a pay-when-paid clause into a pay-if-paid clause, eliminating any guarantee of payment. Courts generally refuse to interpret pay-when-paid clauses this broadly because it would unjustly eliminate the subcontractor's right to compensation for completed work.
Memory Technique
Pay-when-paid = WHEN (timing), not IF (condition). If 'when' becomes 'never' due to insolvency, the courts say the clause is void β the contractor still owes the sub.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor's annual overhead is $480,000 and annual revenue is $2,400,000. For a project with $150,000 direct costs, what overhead amount should be allocated?
Next Question
A structural steel beam connection requires fillet welds with a 1/4-inch leg size around the full perimeter of a 6-inch Γ 8-inch end plate. What is the total length of weld required?
