A structural engineer specifies that concrete must reach 3,000 PSI strength before removing forms. The contractor's schedule requires form removal in 3 days, but the engineer's testing shows only 2,400 PSI. What should the contractor do?

Correct Answer

C) Wait for engineer approval before removing forms

The contractor must follow the engineer's specifications for structural safety. Removing forms before achieving specified strength could compromise structural integrity and violate professional standards. The engineer's approval is required before proceeding.

Answer Options
A
Remove forms as scheduled to maintain timeline
B
Remove forms but leave supports in place
C
Wait for engineer approval before removing forms
D
Request the engineer to lower the strength requirement

Why This Is the Correct Answer

Option B is correct because structural specifications set by engineers are mandatory safety requirements that cannot be compromised. The engineer specified 3,000 PSI for a reason - this is the minimum strength needed to safely support the structure's loads. Since testing shows only 2,400 PSI (80% of required strength), removing forms could lead to structural failure, potential collapse, and serious safety hazards. The contractor must wait for the engineer's professional assessment and approval before proceeding with form removal.

Why the Other Options Are Wrong

Option B: Remove forms but leave supports in place

Removing forms while leaving supports is still unsafe because the concrete hasn't reached the specified strength. The forms themselves provide critical support during the curing process, and partial removal could create uneven loading conditions that the weakened concrete cannot handle safely.

Option D: Request the engineer to lower the strength requirement

Removing forms as scheduled would violate the engineer's specifications and create serious safety risks. The concrete has not reached the required strength to safely support structural loads, and prioritizing schedule over safety could result in structural failure, injuries, legal liability, and code violations.

Memory Technique

Think 'Engineer Says, Contractor Waits' - when structural specs aren't met, the engineer's approval is always required before proceeding with critical construction activities like form removal.

Reference Hint

Florida Building Code Chapter 19 (Concrete) and ACI 318 standards for concrete strength requirements and form removal procedures

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.