A shop drawing submittal for structural steel shows a connection detail that differs from the contract documents but appears to be structurally adequate. What should the contractor do?
Correct Answer
D) Submit the shop drawing to the engineer for review and approval
All shop drawings must be submitted to the design team for review and approval, even if the proposed detail appears adequate. The engineer must verify that any changes maintain structural integrity and code compliance.
Why This Is the Correct Answer
Shop drawings are contractually required submittals that must be reviewed and approved by the design team regardless of how adequate they appear to the contractor. The engineer of record is the only party qualified and legally responsible for determining if structural modifications maintain code compliance and design intent. Even minor deviations from contract documents require professional engineering review to ensure structural integrity and avoid liability issues. This is a fundamental requirement in construction administration and quality control processes.
Why the Other Options Are Wrong
Option B: Modify the detail to match the contract documents exactly
A change order is premature and may be unnecessary - the shop drawing review process will determine if the change is acceptable or if modifications are needed before any contract amendments.
Option C: Proceed with fabrication since the detail appears adequate
Proceeding without approval violates contract requirements and exposes the contractor to significant liability if the connection fails or doesn't meet code requirements, even if it appears adequate to non-engineering personnel.
Memory Technique
Think 'SAFE': Submit All For Engineering review - never assume structural adequacy without professional approval
Reference Hint
AIA A201 General Conditions, Section 3.12 Shop Drawings, Product Data and Samples
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass